SUMMARY OF KSC SEGMENT ASSEMBLY OPERATIONS RH AFT (SRM-25) TO RH AFT CENTER (SRM-26) | ||
---|---|---|
| ||
SEGMENT STACK SEQUENCE - 7 DEC 85 | ||
| ||
ACTIVITY |
TIME |
REMARKS |
| ||
POSITION RH AFT CENTER SEGMENT IN TRANSFER AISLE |
2300 |
6 DEC 85 |
LIFTING BEAM CONNECTED |
0100 |
-- |
JOINT PUTTY APPLICATION COMPLETE |
0120 |
|
FIRST ROUNDNESS MEASUREMENT - 4-POINT LIFT |
0145 |
UNACCEPTABLE |
FIRST ROUNDNESS MEASUREMENT - 2-POINT LIFT |
0300 |
UNACCEPTABLE |
SECOND ROUNDNESS MEASUREMENT - 2-POINT LIFT |
0354 |
UNACCEPTABLE |
THIRD ROUNDNESS MEASUREMENT - 2-POINT LIFT |
0415 |
UNACCEPTABLE |
COMPLETE RH AFT CENTER TANG INSPECTION |
0500 |
NO PROBLEM REPORT |
COMPLETE RH REPAIR, CASE TO INSULATION DEBOND TANG |
0500 |
PR-SR-RAC-050-0001 |
INSTALL. JOINT ROUNDING TOOL TO TANG |
0545 |
016° - 196° LOCATION |
"0" RINGS INSTALLED |
0910 |
|
CLOSEOUT PHOTOS TAKEN |
0915 |
|
REMOVE TOOL AND TAKE ROUNDNESS MEASUREMENT |
0935 |
ACCEPTABLE |
TANG ENGAGED |
1015 |
|
FIRST PIN INSTALLED |
1020 |
|
LAST PIN INSTALLED |
1030 |
|
LEAK CHECK COMPLETED |
1220 |
0.0 PSI DECAY |