LAUNCH DATE CHRONOLOGY | ||
---|---|---|
| ||
JANUARY 25 |
- L-1 DAY REVIEW - 11 AM |
- LAUNCH DAY WEATHER QUESTIONABLE |
|
MISSION MANAGEMENT TEAM (MMT) MTG - 9:30 PM |
- LAUNCH DELAYED TO JANUARY 27 DUE TO WEATHER NO-GO |
| ||
JANUARY 26 |
- MMT MTG - 2:00 PM |
- LAUNCH CONFIRMED FOR 9:37 AM ON JANUARY 27 |
| ||
JANUARY 27 |
- LAUNCH ATTEMPT |
- INITIAL DELAYS: |
|
|
|
|
|
|
|
|
- LAUNCH DELAYED TO JANUARY 28 DUE TO HIGH CROSS WINDS (RTLS) |
|
- MMT MTG - 2:00 PM |
- CONCERN FOR COLD TEMPERATURES AFFECTING FACILITIES SUPPORTING ON TIME LAUNCH |
| ||
JANUARY 28 |
- LAUNCH |
- DELAY IN COUNTDOWN DUE TO GSE PROBLEMS AND FROZEN PIPE |
|
|
- CONCERN FOR ICE ON SERVICE STRUCTURE & MOBILE LAUNCH PLATFORM (MLP) |
|
- TECHNICAL MTG - 8 AM. REVIEW ICE CONCERN REGARDING ORBITER THERMAL PROTECTION SYSTEM |
- DECISION TO: |
|
| |
|
|