[190] FLIGHT READINESS
REVIEW (FRR)
CONTENTS OF REVIEWS (CONTINUED)
- SAFETY - R&QA.
- ALL CHANGES TO CIL'S/HAZARDS AND ALL
APPLICABLE ALERTS.
- NON-CONFORMANCES.
- LSS ASSEMBLY AND CHECKOUT PROCESS
REVIEW.
- UNPLANNED OPEN WORK
- UNPLANNED OPEN WORK AND PLANS FOR
COMPLETION/CERTIFICATION
- SUPPORT OPERATIONS
- REVIEW OF SUPPORT TEAM AND
FACILITIES
- CERTIFICATION OF ELEMENTS
- EACH ELEMENT
- SUPPORT TEAM AND FACILITIES
- SPO BOARD