    ISS Daily Summary Report – 03/13/14

    SpaceX-3 Launch Delayed:  Due to contamination found on the beta cloth shields in the SpaceX-3 unpressurized external trunk, the decision was made to move the launch of SpX-3 to later in the month.  The exact day of launch will be assessed by ground teams.  Specialists are reviewing options for addressing the contamination issue on the …

    Read Full Post

    ISS Daily Summary Report – 03/12/14

    Crew Handover Conference: In preparation for 38 Soyuz (38S) arrival scheduled for March 26, Commander (CDR) Wakata and Flight Engineer (FE)-5 Mastracchio participated in a conference to pass on lessons learned to the 38S Crew. The purpose of this activity is to begin the handover process through videocons and data exchanges between the current crew …

    Read Full Post

    ISS Daily Summary Report – 03/10/14

    36 Soyuz (36S) Departure/Landing: Soyuz 36S undocked from the MRM2 zenith port bringing Commander (CDR) Kotov, Flight Engineer (FE)-2 Ryazanskiy and FE-3 Hopkins back to earth. The undock command, which initiated the opening of the Soyuz vehicle docking hooks was issued at 7:01pm CDT with physical separation occurring a minute and a half later.  The …

    Read Full Post

    ISS Daily Summary Report – 03/07/14

    Water Recovery System (WRS) Status: On February 24th, the Water Processor Assembly (WPA) had a fault due to a leak into the catalytic reactor. On Thursday, Hopkins and Mastracchio successfully R&Rd the catalytic reactor. WPA has since been activated and is processing nominally. On Board Training (OBT) Soyuz Descent: Commander (CDR) Kotov, Flight Engineer  (FE-2) …

    Read Full Post

    ISS Daily Summary Report – 03/06/14

    Water Recovery System (WRS) Catalytic Reactor Remove & Replace (R&R): On February 24th,  the Water Processor Assembly (WPA) had a fault due to a leak into the catalytic reactor (approximately 1 liter of water). Today, Flight Engineer (FE)-3 Hopkins and FE-5 Mastracchio successfully R&Rd the catalytic reactor.  In preparation for the R&R, Hopkins removed Treadmill …

    Read Full Post

    ISS Daily Summary Report – 03/05/14

    Water Recovery System (WRS) In-Flight Maintenance (IFM) Procedure Review: On February 25th, the Water Processor Assembly (WPA) had a fault due to a leak into catalytic reactor (approximately 1 liter of water). The catalytic reactor is scheduled to be removed and replaced (R&Rd) tomorrow.  Flight Engineer (FE)-3 Hopkins and FE-5 Mastracchio conducted a procedures review …

    Read Full Post

    ISS Daily Summary Report – 03/04/14

    Aniso Tubule Light Treatment:  Flight Engineer (FE)-6 Wakata retrieved an Aniso Tubule sample from a Minus Eighty Degree Celsius Laboratory Freezer for ISS (MELFI) and attached a Ziplock bag containing the Sample Chamber onto a Cell Biology Experiment Facility (CBEF) door to expose it to light.  This is the fifth of five planned runs.  Later …

    Read Full Post

    ISS Daily Summary Report – 03/03/14

    Cube Satellite (CubeSat) Closeout Operations:  Today, Flight Engineer (FE) 6 Wakata and FE-3 Hopkins closed out the Nanorack Cubesat Deployer (NRCSD) operations.  This morning the slide table was moved from the Japanese Experiment Module (JEM) Airlock into the JEM Pressurized Module (JPM).  Later, the crew removed the empty Nanoracks Cubesat Deployers (NRCSDs) and Multi-Purpose Experiment …

    Read Full Post